April 15, 2025
WAAP Housing Society continues to make strong progress across all projects. Both the 70-unit and 20-unit developments remain on track for completion by the end of 2025.
To prepare for occupancy, we plan to begin recruiting a building manager and coordinator in Summer 2025.
We’ve also set up a dedicated email for any questions or tenancy inquiries: [email protected]
Details regarding tenancy applications will be announced in late Summer or Fall 2025.
Our 38-unit project is also moving forward steadily. We aim to submit the building permit application by Summer 2025, with construction targeted to begin in late 2025—pending BC Housing approvals—and completion anticipated in early 2027.
Project 1: 70-Unit Housing Development
Status: Under Construction
Expected Completion: December 2025
Key Updates:
• Construction is on schedule
• Building framing complete.
• Mechanical and electrical work has commenced, including rough ins.
• Gypcrete floor topping work has commenced
• Exterior window installation is complete
• Roofing membrane works has commenced
• Interior framing, blocking and backing ongoing,
• Dehumidifiers, heaters and fans are running throughout to dry out the building completely
Project 2: 20-Unit Housing Development
Status: Final Construction Phase
Expected Completion: November 2025
Key Updates:
• Construction is on schedule
• Mechanical and electrical work has commenced, including rough ins.
• Building framing complete
• All windows and doors installed
• Exterior insulation and cladding installation in progress.
• Gypcrete floor topping work has completed
• Roofing membrane works has commenced
• Sprinkler installation in progress.
• Interior finishes to commence soon
Project 3: 38-Unit Affordable Housing Development
Status: Pre-Construction
Expected Construction Start: September 2025
Expected Completion: February 2027
Key Updates:
• Design development is complete, and permit drawings are in progress.
• BC Housing approval milestones are underway.
Challenges:
• BC Housing milestone approvals may cause slight delays.
• Prince Rupert’s higher construction costs present a challenge for funding approvals.
Next Steps:
• Secure building permits.
• Obtain full BC Housing funding approvals.
Summary
All three projects are progressing well. WAAP remains focused on meeting timelines and delivering
quality housing to support the Lax Kw’alaams community. Please contact us with any questions or
for additional details.
Thank you,
Mustafa K.
Lax Kw’alaams WAAP Housing Society




